Why tasks take longer than you think, and how to estimate better
The planning fallacy explained with the numbers from the studies, a worked example, and an estimate-versus-actual sheet that gives you your own buffer.
Tasks take longer than you think because you picture the plan going smoothly and give little weight to how similar tasks went before. Psychologists call this the planning fallacy. In a classic 1994 study, students expected to finish their thesis in about 34 days and took about 56.
In short
- It has a name. The planning fallacy is expecting a task to take less time than it will, even when similar tasks ran long before.
- We plan from the best case. In a 1994 think-aloud study, 74% of what students said while estimating was about the future and 7% about past experience.
- Memory may run short too. A 2005 review argues that people also remember past tasks as shorter than they were, and carry that into new guesses.
- Real numbers help. In 2008 experiments, telling people how long a similar task had actually taken made their next estimate more accurate.
- Use your own ratio as a buffer. Write down guess and actual for a few tasks, and multiply future guesses by your typical ratio.
Your turn: Time one task you do every week, and write the real minutes next to your guess.
On this page
What is the planning fallacy?
The planning fallacy is predicting that a task will take less time than it does, even when you know similar tasks took longer. The best-known evidence comes from Roger Buehler, Dale Griffin and Michael Ross, who published five studies with university students in 1994, several of them relying on people reporting when they finished.1
In the first, 37 psychology students in their final thesis semester at the University of Waterloo predicted when they would hand in their thesis. Among the 33 who had handed it in by the end of the records, the average prediction was 33.9 days. They took 55.5. Fewer than a third of all 37 finished by their own best estimate.1
The researchers also asked for a worst case, the date “if everything went as poorly as it possibly could.” Even then, only 48.7% finished by that date.1 Imagining the worst did not protect people from guessing short.
It happens with small tasks too. In a second study, students named tasks they meant to finish in the coming week. For the non-school ones, such as fixing a bicycle or cleaning an apartment, they expected 5.0 days and took 9.2.1
One encouraging detail: the guesses still carried information. In the thesis study, people who predicted longer did take longer.1 Our estimates are informative and consistently short.
Why do we guess short?
We build the estimate from the plan in our head, and we explain away the times things went over. In Buehler’s third study, students said their thoughts out loud while predicting when they would finish a school project. 74% of what they said was about the future, and 7% about relevant past experience.1
Studies 3 and 4 in the same paper found a second habit: when people remembered running late before, they blamed outside, one-off causes, which made the past seem irrelevant to the next prediction.1
A 2005 review by Michael Roy and colleagues adds another layer. It argues that people do base predictions on memories of similar tasks, and that those memories are themselves too short. “People appear to underestimate future event duration because they underestimate past event duration,” the authors write in the abstract.2
Does listing the steps help?
Listing the steps usually makes an estimate bigger, and for people who guess short that is a step toward the real figure. In three experiments from 2008, Forsyth and Burt asked people to allocate time either to a whole task or to each of its subtasks. The time given to the whole task was consistently smaller than the sum of the times given to its parts.4 They called this the segmentation effect.
The effect depends on what you list. In three studies from 2014, spelling out unusual parts of a task that take long raised estimates, spelling out unusual parts that are quick lowered them, and spelling out the typical parts made no difference.5
So the useful version is targeted. When you break a task down, look for the slow or easily forgotten parts: setting up, waiting, tidying away, the second pass.
What this can’t tell us. Whether a bigger estimate from listing steps was also a more accurate one in these tasks. That depends on how short your first guess was.
Why is your own track record the best estimate?
Because a record replaces the memory that runs short. In 2008, Roy, Mitten and Christenfeld asked college students to predict how long a task would take, such as counting sheets of paper or writing an essay. In two experiments, telling them how long a previous similar task had actually taken them increased the accuracy of their predictions.3 In a third, with people recruited in places like fast-food restaurants, giving them the average time other people had needed worked too.3
Buehler’s fourth study points the same way.1 Students predicted when they would finish a one-hour computer assignment. One group was asked to recall how early they usually finished similar assignments and to describe how that would play out this time. That group’s average prediction matched their actual finishing time. Their predictions were less biased, though no more precise for each individual.
What the research says
ExperimentWhen people use real figures from past tasks, their estimates move closer to reality.13
What this can’t tell us: How well this works over months of real work. The tasks were short and set by researchers.
What does a better estimate look like?
Take a gut guess, list the parts, then check your record. Here is a worked example for “clean the kitchen”. The minutes are an illustration, not data.
Worked example: Clean the kitchen
- Gut guess: 20 minutes.
- List the parts, including the slow ones:
- Clear and stack the counters: 3 minutes
- Load the dishwasher: 7 minutes
- Wash the pans by hand: 10 minutes
- Wipe the counters and hob: 5 minutes
- Sweep the floor: 5 minutes
- Take the bin out: 3 minutes
- Total: 33 minutes
- Check your record: the last three times took 35, 42 and 38 minutes.
- Plan for 40 minutes. The gap between 20 and 40 is the planning fallacy in miniature.
How much buffer should you add?
Use your own ratio of actual to estimated time. Popular rules like “double it” or “add 20%” are easy to remember, and we found no study that tests those specific numbers.
Fill in the sheet for a week or two. For each task, divide the actual minutes by your guess. The middle value of those ratios is your personal buffer. If your typical ratio is 1.4, a 30-minute guess becomes 42 minutes in your calendar.
| Task | My guess (min) | Actual (min) | Actual ÷ guess |
|---|---|---|---|
| Example: weekly report | 30 | 45 | 1.5 |
| Middle value (my buffer) |
Keep separate ratios for kinds of work that differ a lot. A paper notebook, a spreadsheet or a timer you already own is enough. When you plan a whole day in blocks, the same ratio applies to each block; see time blocking for days that don’t go to plan.
Questions people ask
Why do I always underestimate how long things take?
It is very common. When you estimate, you picture the steps going smoothly and give little weight to past delays, which you tend to put down to one-off causes. Your memory of how long past tasks took may also be too short.
Does everyone have the planning fallacy?
It is common, though it isn’t universal. In the 1994 thesis study, about 30% of students finished by their best estimate. The same paper found that observers predicting someone else’s task overestimated the time, so the bias shows up mainly when we predict our own tasks.
Should I just double my time estimates?
Doubling is a popular rule, and we found no study that tests the number itself. It may be too much for some tasks and too little for others. A ratio worked out from your own guesses and actual times fits your work better.
How does this relate to time blindness?
The planning fallacy is about predictions, while time blindness is about sensing time as it passes. They often show up together as running late. See what is time blindness? for the second part.
Sources
- Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the “planning fallacy”: Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366–381.FIVE STUDIES, INCLUDING EXPERIMENTS · UNIVERSITY STUDENTS · STUDIES 1–4: N = 37, 104, 78, 123doi.org/10.1037/0022-3514.67.3.366
- Roy, M. M., Christenfeld, N. J. S., & McKenzie, C. R. M. (2005). Underestimating the duration of future events: Memory incorrectly used or memory bias? Psychological Bulletin, 131(5), 738–756.NARRATIVE REVIEW · STUDIES OF DURATION ESTIMATESdoi.org/10.1037/0033-2909.131.5.738
- Roy, M. M., Mitten, S. T., & Christenfeld, N. J. S. (2008). Correcting memory improves accuracy of predicted task duration. Journal of Experimental Psychology: Applied, 14(3), 266–275.THREE EXPERIMENTS · COLLEGE STUDENTS AND MEMBERS OF THE PUBLICdoi.org/10.1037/1076-898X.14.3.266
- Forsyth, D. K., & Burt, C. D. B. (2008). Allocating time to future tasks: The effect of task segmentation on planning fallacy bias. Memory & Cognition, 36(4), 791–798.THREE EXPERIMENTS · TIME ALLOCATION TO WHOLE TASKS AND SUBTASKSdoi.org/10.3758/MC.36.4.791
- Hadjichristidis, C., Summers, B., & Thomas, K. (2014). Unpacking estimates of task duration: The role of typicality and temporality. Journal of Experimental Social Psychology, 51, 45–50.THREE STUDIES · UNIVERSITY STUDENTS · STUDY 1 N = 152doi.org/10.1016/j.jesp.2013.10.009